Page 88 - High Knob Master Plan
P. 88
PROJECT/INITIATIVES
KEY PARTNERS
ACTION TEAMS
ACTION STEPS
PRIORITY
TIMELINE
Year 1
Year 2-5
Year 5-10
Goal #1: Create / Enhance Destinations
Equestrian Resort
High Knob Entity
Scott County Horse Park USFS
Capital Improvements
> Program / develop project > Seek partners
> Pursue / secure grants and partners > Contract A/E services
> Construct and operate project
High
Dark Lodge
High Knob Entity Scott County EDA
Capital Improvements
> Program / develop project > Seek partners
> Pursue / secure grants and partners >Acquire land
> Contract A/E services
> Construct and operate project
Medium
Big Cherry Campground Resort
High Knob Entity Big Stone Gap
Capital Improvements
> Program / develop project > Seek partners
> Pursue / secure grants and partners > Contract EIS and A/E services
> Construct and operate project
Medium
Winter Sports Development Area: back county skiing, ice skating, year-round tubing
High Knob Entity
High Knob Development Corporation
Norton
Capital Improvements
> Secure partners > Secure financing
> Contract A/E services
> Construct and operate project
Low
Goal #2: Improve Access to Regional Destinations
New Devil’s Bathtub Parking Lot
Friends of SWVA Scott County USFS
Capital Improvements
> Secure grants
> Phase 1: Program / design/ construct
> Secure grants
> Next phase(s): Program / design/ construct
High
High Knob Destination Center
Friends of SWVA Norton
USFS
Capital Improvements
> Secure grants
> Contract A/E services
> Construct project
High
88 CHAPTER 10: IMPLEMENTATION HIGH KNOB REGIONAL INITIATIVE
Principle #6: Prioritize on initiatives that allow a sustainable mix of year-round activities and businesses