Page 88 - High Knob Master Plan
P. 88

 PROJECT/INITIATIVES
KEY PARTNERS
ACTION TEAMS
 ACTION STEPS
 PRIORITY
TIMELINE
Year 1
Year 2-5
Year 5-10
      Goal #1: Create / Enhance Destinations
 Equestrian Resort
  High Knob Entity
Scott County Horse Park USFS
   Capital Improvements
  > Program / develop project > Seek partners
  > Pursue / secure grants and partners > Contract A/E services
 > Construct and operate project
  High
   Dark Lodge
  High Knob Entity Scott County EDA
   Capital Improvements
  > Program / develop project > Seek partners
  > Pursue / secure grants and partners >Acquire land
> Contract A/E services
 > Construct and operate project
  Medium
   Big Cherry Campground Resort
  High Knob Entity Big Stone Gap
    Capital Improvements
   > Program / develop project > Seek partners
   > Pursue / secure grants and partners > Contract EIS and A/E services
  > Construct and operate project
   Medium
    Winter Sports Development Area: back county skiing, ice skating, year-round tubing
 High Knob Entity
High Knob Development Corporation
Norton
   Capital Improvements
  > Secure partners > Secure financing
  > Contract A/E services
 > Construct and operate project
  Low
   Goal #2: Improve Access to Regional Destinations
 New Devil’s Bathtub Parking Lot
  Friends of SWVA Scott County USFS
   Capital Improvements
  > Secure grants
> Phase 1: Program / design/ construct
  > Secure grants
> Next phase(s): Program / design/ construct
   High
   High Knob Destination Center
  Friends of SWVA Norton
USFS
    Capital Improvements
   > Secure grants
> Contract A/E services
   > Construct project
     High
                  88 CHAPTER 10: IMPLEMENTATION HIGH KNOB REGIONAL INITIATIVE