                                                                                                                                                             6 NEC 210.52(C)(1), (2), and (3) The number of 7 NEC 230.67 All services supplying a house will
outlets serving islands and peninsulas in a kitchen has been totally rewritten. A square foot formula
will now be used to determine how many outlets
are needed in these areas. Traditionally, one outlet could be used to serve islands and peninsulas. Using this formula some may now require 2, 3, or 4 outlets. Some minor changes have been made about where these outlets can be installed. Outlet locations will have to be addressed during the design phase.
now have a Type 1 or Type 2 whole house surge protection device (SPD).