                                                                                                           Sales Surtax Update
The half-cent sales surtax, approved by Brevard County voters in 2014, provides funding for critical facility renewal, educational technology and security projects throughout the school district. Each month, BPS News will profile a Brevard County school that has benefitted from the sales surtax. To learn more about your money at work, visit us on Facebook at Brevard Public Schools – Facilities Services.
West Shore Jr./Sr. High School
Age of School: 62 years
Project Type: Complete HVAC renewal
Project Overview: This project started out of sequence because of a failing HVAC system. The new more efficient system is water cooled using cooling towers and chillers, as well as full piping to supply the new system. Because of time and funding restraints the project was separated into two phases to be completed over two summers. Designing of this project started around July 2017 with the comple- tion of phase one expected by March 31, 2019 and phase two on/before October 8, 2019.
Canaveral Construction Company, Inc. is the design/build contractor managing the project. TLC Engineering for Architecture, Inc. is the design team. Brevard Public Schools project manager is Jim Hudson.
                                                                                                                                     Cost: Phase 1 - $1,999,629.00 Phase 2 - $1,518,350.00