The lift interior and exterior (this was never part of the approved specification)
Artifacts grills
The handrails
The flooring
The BT wiring
The various interior woodworks
Replacing all brassworks throughout the building
Changing the rear locks
Buttoning on interior cupboards
Installation of signage throughout the building
The lighting and electrics [by qualified NICIEC electrician]
"And [per Mr Brown-Constable] probably a lot more"
As stated above, the original budget for the refurbishment was £105,019. This had been understood by the leaseholders to be the contract price tendered by AR Lawrence. However according to a letter from Mr Brown-Constable dated 14 June 2016 (see Item 6) this budget was in fact made up of two separate elements, namely £91,321 (the anticipated bill from AR Lawrence) and £13,698 (the anticipated bill from the surveyors Evens Boyce and Carpenter).
It is fair to say that the lessees had not actually understood that the surveyor's charges were included in the original £105,019 budget, since MHML's Section 20 letter of 22 June 2014 had referred only to the cost of engaging AR Lawrence. No mention had been made of the surveyors. And in a subsequent e- mail of 11 September 2014 (see Item 7) Mr Brown-Constable confirmed to Mrs Hillgarth that the works "are being done by your preferred contractor A&R Lawrence for the agreed budget of £115,019".