Page 180 - xxxxxx9_BEGG_ALL_MASTER to Add to
P. 180

-32-
“HOW DID YOU THINK MHML WERE FUNDING THE NEW LIGHTING?”
various reasons, none of which are legitimate or excusable but I regret somewhat predictable, as evidenced in correspondence weeks and months ago.
It would be helpful if those same lessees and any other of the same opinion confirm they are now not willing to contribute the required additional funds to adequately cover the agreed £105,019 budget plus any unexpected contingencies as well as any panics within Mitre House generally (the lift, leaking pipes etc).
Management will then re-assess the schedule of works and reduce certain workings,
cancel the terrazzo floor renovation, instruct one colour painting throughout the interior and most regretfully cancel the communal tv aerial install, scheduled for next Thursday/Friday.
Management is a limited company and cannot trade legitimately unless sufficient funds are in place to cover legally signed contracted workings. It's illegal and at present we're illegal but only until Monday 22nd midday.
Also those lessees who have paid to date will be immediately re-imbursed.
Management will make all the above re-scheduling and cancellations on Monday 22nd Sep- tember at midday unless we hear back with good news from all lessees intending to honour their agreements (or not as the case may be), and our decision, if made, to abort certain workings will not be reversible, like the Scottish Referendum...!
Notification was also posted on our www.mitrehouse.com See following page:
PLEaSE rEFEr to variouS attaCHED “PDF/FuRtheR ReFeRenCes” in SuPPort oF arguMEnt
























































































   178   179   180   181   182