disputed proposed Internals, and an equally equitable compromise to sort your other disagreement, namely to postpone the Externals until next year. See RED section (A) and (B) below.”
If the above is case, then please let’s put this to bed.
You can then carry on ignoring the requests for clear descriptions of works from your chosen contractors, we can take them out of the equation, and everyone will be happy and we can start sorting dates for the works to commence.
I would ask everyone copied in to reply to Management confirming their agreement to:
  - - -
Using Wade as the contractor for ALL the internal works. Delaying exterior works until 2015
ONCE and only ONCE the interiors are completed, re-visit the
discussion on the exterior with regard to costs, and financing options for the additional funds, needed and who is to be given the contract.
I attached documentation to my previous e-mail sent on 1st May, which clearly shows past precendence that decisions taken by management were under the direction of the majority of the leasees at Mitre House. So let’s carry on the tradition.
Best Wishes, Michele
<CCE00000.pdf><Untitled attachment 00503.htm><img780.pdf><Untitled attachment 00506.htm> <office.png><Untitled attachment 00509.htm>
<yyyGraffiti INK Logo EMAIL.png>
Graffiti Editions Ink / Designers
7 Mitre house 124 Kings Road Chelsea London SW3 4TP Telephone +44 (0)20 7589 2764 Mbl +44 (0)798 33 33 543 www.Graffitieditions.Com Email: Studio@Graffiti.Biz
This message, and any and all attachments, are for the intended recipient(s) only, and may contain information that is privileged, confidential and/or proprietary and is subject to important terms and conditions available at www.suegrabbit&run.com/cocktail_lounge. If you are not the intended recipient, you are strongly advised in law to delete this message before it explodes - you have been warned!.
   



















































































   62   63   64   65   66