Projects History
At Iron Creek, we have had the opportunity to be involved in a number of high-pro le, remote projects ranging from isolated islands in Alaska to Canada’s far north and even Antarctica. The scalable nature of our technology is perfectly suited to deploy to the most remo- te regions on earth and we thrive on the challenges presented by operating in these environments. Project safety is built in to all our operationsfromtheverystartofourprojectplanningtotheendofourdemobilizations. Forus,it’snotjustacompanyrequirement,it’s an embedded culture. From our most senior management to our on-site work crews, our entire company strives to nd ways to work smarter and safer. The lollowing is a list of projects that have been completed under the supervision of either Chad Belenky or Roger Richter - using the ETC & M1 Infrared Technologies:
ETC Completed Project: Progress Energy Canada Ltd, Northeast B.C., Canada
Consultant:
Project Manager: Client:
Project:
Soil Volume:
Soil Type: Contamination Type: Pre-treatment levels: Post-treatment levels: Authority:
EBA Tetra Tech
Contact information available upon request Progress Energy
Jedney Gas Fields
23,000 tons
Heavy Clay
BTEX, VPH6-10, LEPH10-19
All above provincial Contaminated Sites Criteria
All below regulatory criteria (most below detection limits) BC Oil & Gas Commission
ETC Completed Project: Chevron Canada, Yukon Territory, Canada
Consultant:
Project Manager: Client:
Project:
Soil Volume:
Soil Type: Contamination Type: Pre-treatment levels: Post-treatment levels: Authority:
Parkvalley Consulting Ltd
Contact information available upon request
Chevron Canada
Legacy Cleanup
2,000 tons
Saturated tight Clays, uvial material & some permafrost Diesel, BTEX, LEPH10-19, HEPH19-32
All exceeding territorial Contaminated Sites Criteria.
All meeting the territorial Contaminated Sites Regulation Yukon Government