Testing & Commissioning
All mains powered devices should be inspected to ensure the wiring is correct at the
terminal block i.e. Live, Neutral and IC are correctly assigned.
•
When mains supply is present a Green LED is visible on the device.
•
Test the interconnection by pushing the test button on each Alarm in turn.
•
All other interconnected Alarms will sound.
•
The Alarm sounding on button test verifies that the sensor, electronics, and sounder are
working.