Testing & Commissioning
All mains powered devices should be inspected to ensure the wiring is correct at the terminal block i.e. Live, Neutral and IC are correctly assigned.
• When mains supply is present a Green LED is visible on the device.
• Test the interconnection by pushing the test button on each Alarm in turn.
• All other interconnected Alarms will sound.
• The Alarm sounding on button test verifies that the sensor, electronics, and sounder are working.
             ATTIC
             Connection to Distribution Board
Whole system data collection and wireless RF interconnection via the Gateway and wireless RF enabled Alarms and accessories throughout the property
 44