Page 36 - SAPREF 50 year
P. 36

 Turnaround in numbers:
The 2013 Turnaround was the biggest in SAPREF’s 50-year history. It was a real feat of engineering and project management. But how big is a big Turnaround? The numbers below answer the question best:
 Manpower peak
 6800
Bolts replaced
 250 000
 Tons of new structural steel installed
173 tons
Breakfast packs
 390 000
Bus trips
 2080
Cabling
 35km
 Carbon steel piping installed
3330 metres
 Studbolts procured and installed
18 842
Columns completed
 54
Cranes
 69
Scaffolding erected
 2900 tons
Compressors on site
 50
Diameter Weld Inches
 37 000
Heat Exchangers
 242
Refractory
 385m2
RVs overhauled
 314
 Scrap metal
500 tons
 Spades installed and pressure tests
6200
Trenches
 4,5km
Vacuum trucks
 9
Vessels completed
 136
Work packs
 2860
 Schedule (actual vs. plan)
65 days vs. 63 days
                        And yet, despite the amount of work and the number of people the safety statistics tell a story of discipline, skill, leadership and world class safety management:
 LTIs (Lost Time Injuries, that is, injuries that result in a person being away from work for at least a shift)
  0
 Fires
2
 First Aid Cases
52
 Medical Treatment Cases
1
 LOPCs (loss of primary containment)
 2
  SAPREF: FUELLING SA FOR 50 YEARS
32
   The Cat Cracker reactor top, complete with cyclones and diplegs, smoothly rises out of the shell to be replaced by a complete new assembly during the 1985 Turnaround.
  




































   34   35   36   37   38