Page 16 - WTC Introduces Project Thrive at The Impact Center
P. 16
16
Completed 11/2014
Theater/Banquet Room Of ces
Conference Room Break Room Restrooms
Target 9/2015
Classrooms
Library
Chapel
Playground
Locker Rooms Fitness Center REACH Center Game Rooms Multi-purpose Room
Target 3/2016
Of ces Administration Counseling Suites Music/Recording Studio
Video Production
Target 12/2016
Sanctuary/ Performing Arts Center
Green Room In rmary Restrooms
Target 3/2017
Catering Kitchen Bookstore
Café
Target 8/2017
Building Exterior
Project Budget $9.6M
10%
8%
4%
27%
Project Size 125,500 sf
4% 11% 49%
...because how we
22%
23% 6%
n Purchase n Phase 1A n Phase 1B n Phase 2 n Phase 3 n Phase 4 n Exterior
28% 8%
Project Budget & Timeline
PHASE 1A
PHASE 1B
PHASE 2
PHASE 3
PHASE 4