Page 136 - Manual for Activities directed at the Underwater Cultural Heritage
P. 136

 © T. Maarleveld. Financial monitoring of expenditure should be combined with monitoring of the exertions and their efficiency. In the multiyear Aanloop Molengat project, an analysis of bottom time was made in relation to primary and supportive tasks.
In the second graph invested manpower is expressed in fieldwork man-days. As this was
a public archaeology project,
it involved a mixed team.The Aanloop Molengat site lies offshore in the North Sea, exposed to the predominantly westerly winds in just 16 m of water. The project comprised the excavation of a ship laden with ingots of lead
and tin from Poland and Czechia among other consignments. It showed that the ship departed from the Dutch Republic in 1635 or shortly after. It was a ship of considerable size as its cargo weighed more than 600 tons.
 Structure of a funding request
Executive summary
Project description including:
• description of planned activities, timetable,
methods and specialists involved
• discussion of preliminary studies and signi-
ficance of site and proposed project
• expected results and deliverables
• expected spin-off
Description of competence and qualifications including:
• reference to previous successful projects of the
research director
• CVs of key staff
• copies of appropriate publications, videos,
press-clippings, etc.
Funding plan including:
• detailed, balanced budget estimates, signed
and dated by the legal representative of the project
Administrative information including:
• Letter by research director explaining funding
scheme, the amount of assistance requested and
its specific purpose
• Name, address, e-mail and telephone of re-
gistered office of the organization promoting the
project
• legal status and statutes
• names, addresses and positions of those in
charge of the project
• a balance sheet for the past year of the body
promoting the project
• bank references
• signed references of the other financial partners
who have already agreed to participate
A golden rule for all projects is never to leave out the technical parts of the dossier, i.e. the details of the administrative and financial aspects.