Page 15 - KML Carpenters Magazine, Summer 2019 KML Carpenters Magazine, Summer 2019 KML Carpenters Magazine, Summer 2019 KML Carpenters Magazine, Summer 2019 KML Carpenters Magazine, Summer 2019 KML Carpenters Magazine, Summer 2019 KML Carpenters Magazine, Summer 2019 KML Carpenters Magazine, Summer 2019 KML Carpenters Magazine, Summer 2019 KML Carpenters Magazine, Summer 2019 KML Carpenters Magazine, Summer 2019
P. 15

LOCAL 252
International Woodworkers Fair Tradeshow
Atlanta, GA
Number of Attendees: 50,000 Project Cost: $40,000
World's Largest Woodworking Tradeshow
FABRICATION TIMELINE:
START: JUNE 2016; END: AUG 2016
LOCAL 253
99 Hudson
Jersey City, NJ
Number of Carpenters: 80 Project Cost: $500 Million
Work Hours: 575,000
START: 2016; END: 2019
LOCAL 254
New Brunswick Performing Art Center/ Crossroads Theater New Brunswick, NJ
Number of Carpenters: 50 Project Cost: $190 Million
Work Hours: 250,000
START: 2018; END: 2019
LOCAL 420
Shell Cracker Plant
Beaver County, PA
Number of Carpenters: 1,200 Project Cost: $6.5 Billion
Work Hours: 650,000
START: 2017; END: 2022
LOCAL 423
Fairview Energy Gas Plant
Johnstown, PA
Number of Carpenters: 100 Project Cost: $1 Billion
Work Hours: 210,000
START: 2017; END: 2020
LOCAL 255
The Beach at South Inlet
Atlantic City, NJ
Number of Carpenters: 100 Project Cost: $72 Million
Work Hours: 112,000
START: 2016; END: 2018