TGB DRUM EXERCISE RIG –
INSTALLATION
&
COMMISSIONING DETAILS
(a) Place the test equipment on a rm solid base in a place having proper level.
(b) The machine placed in such an environment, it should be moisture & dust free
and a protected place from rain.
(c) There must be clearance between machines to wall or machine to other
machine at least 24 inch should be maintained.
(d) One 3 phase AC supply with line to line 415 Volt ± 10% with 50HZ having a
capacity of 1 kilowatt i.e. 6 Amps per phase is required.