TGB DRUM EXERCISE RIG –
                                              INSTALLATION

                                                          &
                                    COMMISSIONING DETAILS











                       (a)    Place the test equipment on a rm solid base in a place having proper level.


                       (b)    The machine placed in such an environment, it should be moisture & dust free
                            and a protected place from rain.


                       (c)    There  must  be  clearance  between  machines  to  wall  or  machine  to  other
                            machine at least 24 inch should be maintained.



                       (d)    One 3 phase AC supply with line to line 415 Volt ± 10% with 50HZ having a
                            capacity of 1 kilowatt i.e. 6 Amps per phase is required.