Page 14 - Demo - Department Eastern Cape Education COLOSA SENIOR
P. 14
PROFESSIONAL FEE SPLIT
Fee Apportionment
STAGE 1-4 STAGE 5 STAGE 6
PA/Architect
Fee %
Quantity Surveyor
R 1,005,967.71 R 603,580.63 R 402,387.08
Fee %
Civil /Structural
Fee %
Elect/Mech
R 236,596.69 R 138,014.73 R 19,716.39
Fee %
OHS
Fee %
SOCIAL FACILITATOR
Fee %
TOTAL FEES
R 1,468,689.60 R 566,494.55 R 62,943.84
R 98,289.91 R 458,686.24 R 98,289.91
R 58,973.94 R 275,211.74 R 58,973.94
70% 27% 3%
Disbursements and other fees
Total Fee Budget Incl. VAT
50% 30% 20%
R 561,481.69 70% R 200,529.18 25% R 40,105.84 5%
R 802,116.71
60% 35% 5%
15% 70% 15%
15% 70% 15%
R 3,429,999.55 R 2,242,517.08 R 682,417.00 R 6,354,933.63 R 877,422.12
R 7,232,355.75
TOTAL FEES INCLUDING VAT
PA/Architect
Quantity Surveyor
Civil /Structural
Elect/Mech
OHS Consultant
Social Facilitator
Disbursements and other fees
Fees Budget incl. VAT
R 2,098,127.99
R 2,011,935.42
R 394,327.81
R 655,266.07
R 393,159.63
R 2,098,127.99 5% R 2,011,935.42 5% R 802,116.71 1.95% R 394,327.81 0.96% R 655,266.07 2% R 393,159.63 0.95% R 877,422.12 2% R 7,232,355.75 18%