Najd complex gate assessment:
On May 15, 2018, the CRISOD team, consisting of RSOD Supt. and Security Supervisor I, conducted risk assessments
for Najd Complex Gate#5, to address the security upgrades for the gate. Observations and recommendations were recorded in a report and addressed to ISSD to consider upgrading the gate in their upcoming BI projects.
Najd Complex Gate#5
Risk Assessment Report for Najd Complex Gate#5
East/West pipelines corridors assessment
On September 16, 2018, Security Risk Assessment Consultants from ISSD along with CRISOD and EWPD representatives, conducted site visits for all pipelines corridors from PS#1 to PS#11. The final report is in its final stage of completion.
Performance Management
55