SD37 Project Update
Work is moving right along on the SD37 project. The signal lights were put up on Wednesday, but it will be up to three weeks before they are operational. The new entrance into the north substation will be done soon and work has begun on the street lighting. More sidewalk and curb will be poured in the next day or two.
The cross-over on Third Avenue has been moved back to Fifth Avenue. Construction will soon begin on Phase 6 which is from Railroad Avenue to Aspen Avenue on SD37. During that construction time, there will be one lane of traf c with aggers during the day and both lanes opened up at night.