PROJECT TIME-LINE
32 Months to Grand Opening Jan 2019
Purchase period and company restructure
April 2019
Construction design work will begin
July 2019
Final approval for designs and construction
Nov 2019
Demolition of current structures and deep water dock & birthing
Feb 2020
Laying foundations and ground works and main island structures
March 2021
Main Residence and additional building’s interior work begins
Sept 2021
Final interior nishes, gardens and island amenities installations
Nov 2021
Soft Launch
Dec 2021
First Guest Arrival for Christmas and New Year Charter