PROJECT DEVELOPMENT AND SERVICES 8.1 Commercial - Lump Sum Fee (continued) Director Senior Project Manager Project Manager Project Coordinator Stage 1 - Concept Design Stage 2 - Design Documentation Stage 3 - Tender Stage 4 - Construction Included but not charged $77,064 $39,520 $55,657 $46,800 $68,250 $9,750 $39,000 Project Manager $172,241 As required min 1-3 days/week depending upon phase min 1-3 days/week depending upon phase min 1-3 days/week depending upon phase Architect $163,800 As needed - 4 weeks As needed - 4 weeks 1 day/week < CONTENTS > 61