  DESIGNING TO A SCHEDULE Created by Nehmer and HVS Design
Determining the budget for a project is just one step in the renovation process. It is also important to develop a thorough and achievable project schedule to help make the project a reality. We have put together the following conceptual schedules to serve as a guide when creating your own project schedule.
• Full-service Hotel
• Select Service Hotel – Prototype Design
• Select Service Hotel – Custom Design
These schedules are not intended to be one size fits all. Each project is unique. However, these durations can assist you and be a check point when developing your project-specific schedule.
    ID
1 2 3 4 5 6 7 8 9 10 11
FUFLuLllSSEeRrvViIcCeEHoOteTlEL Sample Renovation Schedule
Sample Renovation Schedule
  1st Half 2nd Half 1st Half 2nd Half
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
            Start Full Service Design Process 5/30
Design Documents
8 wks Create a Model Room Package
6 mons
12 wks
   Order Model Room Furniture
Model Room Approval1 wk
Update Design with Model Room Comments 3 wks Order FF&E Permitting and Bidding
16 wks
  2 mons
  Date: Thu 5/20/21
Task
Split
Milestone Summary
Project Summary Inactive Task Inactive Milestone
Inactive Summary Manual Task Duration-only
Manual Summary Rollup Manual Summary Start-only
Finish-only Page 1
External Tasks External Milestone Deadline
Progress
Manual Progress
Construction
5.5 mons
 Brand to Confirm PIP Compliance2 wk
s
  96
NEHMER and HVS DESIGN | HOTEL COST ESTIMATING GUIDE 2021