Page 47 - TURKRptJun22
P. 47
YEKA Tenders
Tender
Plant
Capacity (MW)
Best Bidder
Guarantee
kWh
Mar-2017
YEKA GES-1
Konya Karapinar
1,000
Kalyon - China Electronics Technology Group (CETC)
15-year
$0.699
Aug-2017
YEKA RES-1
6 plants
1,000
Kalyon, Siemens Gamesa, Turkerler
15-year
$0.348
Jun-2018
YEKA DRES-1
Off-shore (Gelibolu, Saroz, Kıyıkoy)
1,200
DELAYED (no time set)
50 TWh
$0.800
May-2019
YEKA RES-2
4 plants
1,000
Enerjisa (ENJSA) 2 x 250 MW; Enercon (Germany) 2x 250 MW
15-year
$0.394
2019
YEKA GES-2
3
1,000
CANCELLED
15-year
$0.650
May-2021
YEKA GES-3
74 mini
1,000
-
15-year
TRY 0.218
-
YEKA GES-4
3 plants DONE (16)
300 (1,000)
PARTIALLY DELAYED, Price ceiling amended
23 GWh
TRY0.95 (TRY0.40)
Mar-2022
Nigde
BOR-1
100
Smart Gunes (SMRTG)
0.375
Mar-2022
Nigde
BOR-2
100
Ecogreen
0.390
Mar-2022
Nigde
BOR-3
100
Kalyon
0.427
Jun 21, 2022
Hatay
ERZIN-1
100
DELAYED
Jun 21, 2022
Hatay
ERZIN-2
100
DELAYED
Jun 21, 2022
Sanliurfa
VIRANSEHIR-1
50
DELAYED
Jun 21, 2022
Sanliurfa
VIRANSEHIR-2
50
DELAYED
Jun 21, 2022
Sanliurfa
VIRANSEHIR-3
50
DELAYED
Jun 21, 2022
Sanliurfa
VIRANSEHIR-4
50
DELAYED
Jun 21, 2022
Sanliurfa
VIRANSEHIR-5
50
DELAYED
Jun 21, 2022
Sanliurfa
VIRANSEHIR-6
50
DELAYED
Jun 21, 2022
Sanliurfa
VIRANSEHIR-7
50
DELAYED
Jun 21, 2022
Sanliurfa
VIRANSEHIR-8
50
DELAYED
Jun 21, 2022
Sanliurfa
VIRANSEHIR-9
50
DELAYED
Jun 21, 2022
Sanliurfa
VIRANSEHIR-10
50
DELAYED
May 31, 2022
YEKA RES-3
42 plants
850 (2000)
PARTIALLY DELAYED
35 GWh
TRY0.95 (TRY0.40)
Adana
50
DELAYED
Adiyaman
40
4 bids
Afyonkarahisar
50
DELAYED
Agri - Igdir
20
DELAYED
Aksaray - Kirsehir - Nevsehir
70
DELAYED
Amasya - Samsun
40 (60)
14 bids
Ankara - Kirikkale - Cankiri
50
6 bids
Antalya
60
DELAYED
Ardahan - Kars
20
DELAYED
Artvin - Rize - Trabzon
20
4 bids
Bartın - Zonguldak - Karabuk
20
3 bids
Batman - Mardin - Diyarbakir - Sanliurfa
40
4 bids