gas export volumes will decline sharply over the next few years – indeed they are likely to be down by around 45%
in 2022. Having sold 150bcm to the EU in the form of pipeline gas and LNG
in 2021, current projections see this figure falling to around 80bcm in 2022, with the 35bcm sold to other European countries also likely to decline sharply.
In revenue terms this decline in sales volumes has been more than compen- sated for by the ten-fold increase in
gas prices in Europe, and Gazprom will make record export revenues in 2022. Nevertheless, the search for alternative markets is being stepped up to secure the long-term future of the Russian
gas industry. Asia remains the obvi-
ous target, with China to the fore, but the process will not be instantaneous. Whereas oil can be loaded onto tankers and transported anywhere in the world, the vast majority of Russian gas is trans- ported by pipeline and for historical and geographic reasons these are mainly pointed towards the west. Indeed, in terms of available capacity, Russia’s export pipelines to Europe could be carrying well over 250bcm per annum
if fully utilised.
As mentioned above, Gazprom has struck one deal with China already as in 2014 a long-term contract was signed with CNPC to supply up to 38bcm per annum through the newly constructed Power of Siberia pipeline running from East Siberia to NE China. The political nature of the deal was underlined by the fact that President Putin’s presence in Beijing was required to finalise the agreement, but with his help a contract was signed and pipeline construction began in 2014. It was completed 5 years later in 2019, when gas started flow- ing, and volumes are currently being ramped up towards their plateau level, which is expected to be reached in 2024 or 2025. Current volumes are around 16bcm per annum.
Gazprom had been making plans to expand its sales to China prior to 2022, and these have now been accelerated. The first option is relatively simple and involves the expansion of the exist- ing contract from 38bcm to 44bcm per
annum via Power of Siberia. Gazprom CEO Alexei Miller has already discussed this with his Chinese counterparts and it looks likely to be agreed, with the volumes being added in the second half of this decade.
A second option is to use an existing pipeline in the Far East of Russia, which runs from the island of Sakhalin to Vladivostok, to create a spur line into NE China for exports of gas from new fields offshore Sakhalin. The potential is for volumes to reach up to 10bcm per annum to China (adding to volumes already being used domestically in Russia), and President Putin announced that an agreement had been reached with China in February 2022. However, sanctions have hindered the devel- opment of the gas fields that will be needed to fulfil any future contract and as a result progress has stalled and tim- ing is somewhat uncertain.
The largest, and most interesting project for Gazprom involves bringing gas from West Siberia that would otherwise have gone to Europe and re-directing it towards China. Originally called Power of Siberia 2, this line was conceived as flowing gas from Russia into western China at the border between the Amur region of Russia and
Mongolian border, from where a new transit pipeline named Soyuz-Vostok would take the gas across Mongolia and into Northern China. Gazprom
has apparently agreed the terms of a transit contract with the Mongolian authorities, but it remains unclear what the Chinese reaction is to this new route and the volumes of gas involved. In theory the gas, if priced competitively, should be welcome in an expanding Chinese gas market by the end of this decade, but as yet there has been no official word from the Chinese authorities. With that in mind and considering the length of negotiations over Power of Siberia, it seems unlikely that gas could flow before 2027 at the earliest, with the end of the decade
a more likely start date.
Russia also had major plans for growing its LNG business prior to February 2022, and although these are still theoretically in place it is likely that the impact of sanctions will delay progress as much of the liquefaction technology comes from the West. Two main projects, Sakhalin 2 and Yamal LNG, are currently in operation with a combined capacity of 35bcm. Around two thirds of this is already being sold in Asia, but the remaining 14bcm that was sold in Europe in 2021 could easily
“The largest, and most interesting project for Gazprom involves bringing gas from West Siberia that would otherwise have gone to Europe and re-directing it towards China”
Xinjiang in China. However, this would have put it into direct competition with gas from Central Asia and would have necessitated significant upgrading of pipeline infrastructure inside China, and as a result negotiations have never reached a conclusion on the proposed 30bcm per annum contract.
Instead, a larger 50bcm per annum deal has been proposed by Gazprom which would essentially involve the re-direction of Power of Siberia 2 to the
be re-directed. However, plans for a new project (Arctic LNG-2) have been somewhat stalled, as although the first train is almost complete and is likely to start up in 2023/24, the remaining two trains have been delayed. As a result, another 9bcm could be sold to Asia
by 2025, but beyond that it remains unclear whether further expansion will be possible. Novatek has developed
its own Arctic Cascade liquefaction process, which can work at smaller scale, but plans for 100bcm of export