Page 21 - Lifestyle Outlets Glasgow Harbour Board Proposal
P. 21

2018
2019
2020
2021
M
A
Application submitted June
Planning determined December
Construction tender issued January
Anchor/Key Tenants Marketing Packs
Leasing Percentage of space at year end: 35%
Negotiations/Secure First Tranche Packs
A
M
A
M
A
M
A
Further Premium Brands Negotiation/Secure Leases
Leasing Percentage of space at year end: 60%
Further Mass Market Brands Negotiation/Secure Leases
Start on site October
Further Push in Negotiations to secure Premium and and Mass Market brands
Leasing Percentage of space at year end: 70%
Centre 0pens
Leasing Percentage of space at year end: 80%
Two year build
Open October
2022
Final Leasing to late adopters
Leasing Percentage of space at year end: 100%