Page 39 - Craft of Whiskey Distilling
P. 39
26 | CrAFt oF WHIskEy DIstIllInG
system and must be accounted for to achieve consistent results. The biggest thing that this calculation does not account for is the water that remains after you have stopped sparging. To sparge properly you must maintain the 1.5 to 2” of sparge water above the top of the grain bed to ensure that all of the mash is rinsed equally. Since the geometry of mash tuns can vary, the amount of additional sparge water you will need to prepare will also vary from system to system. The first time you produce a mash, make sure to have more water prepared than you will need. Take detailed water usage notes from that session and then you will know the right volumes of water for subsequent batches.
The above calculations can be done for you using inexpensive software that also helps with formulation and fermentation tracking. The best one is ProMash which has a very robust set of tools that is well suited to mashing and fermentation for a distillery. ($24.95, www.promash.com).
pREpARE THE COMbI-TuN
• Introduce the foundation water through the grist hydrator. This pre-heats the mash tun. Stop the fill when the water level is 1 to 2” above the mash screen.
• Begin introducing the hot liquor and grain simultaneously through the grist hydrator. Control the introduction of both water and malt so that while constantly stirring the two with a mash paddle, you can produce a smooth mash with no lumps. For a seven barrel mash, this should take at least 30 minutes.
• Once dough in is complete, put the mash tun cover back on to help retain heat. Take a temperature and pH reading to see how close you came to the target of 145 deg. F (62.8 C) and pH 5.2. If you did not nail these targets, make a note of how far you were off so you can determine what adjustments are required for subsequent batches.
• Re-set the hot liquor tank’s temperature controller to 190 deg. F (195 deg. F — my 12 deg. F temperature loss would result in a 183 deg. F sparge water temperature. This is to prepare the water for sparging. If you have a recirculation loop (hopefully!) serving the hot liquor tank, make sure it is operating to prevent temperature stratification. The reason for the high temperature is to reduce the viscosity (thickness) of the mash liquid so it runs off freely. Although viscosity reduction is desired in runoffs for beer production, this high of a temperature is not used because it would carry over tannins into the finished product
rendering it harsh. Since we are distilling off the liquid, this is not a concern.
• After the mash has set for 45 minutes, take a small sample of the runoff, filter it through a coffee filter to remove any grain specks and test it for conversion using tincture of iodine. (see procedure in definitions section). If the test is negative, you can begin sparg- ing, otherwise, you must continue mashing until you reach a negative result.
• After the mash has passed the iodine test, introduce the sparge water slowly and in- directly so that it does not channel the mash. Allow the water level to rise 1.5 to 2 inches above the mash bed before starting the runoff. Slowly allow the wort to runoff at the same rate as you are introducing the sparge water. Doing so any faster will run the risk of plug-