The FLEXCAVES™ development timeline follows a structured approach, ensuring efficient execution from
site selection to grand opening. The project is expected to take 14 months from site selection to full
operations, with fundraising, permitting, and marketing efforts running in parallel.
Phase 1: Site Selection & Pre-Development (0-3 Months)
•
•
•
•
•
Identify and secure the ideal site in Southern Kansas City.
Conduct due diligence, zoning approvals, and entitlement processes.
Finalize engineering, architectural plans, and all required drawings.
Launch simultaneous fundraising efforts to align capital with development needs.
Execute purchase agreements and close on the selected property.
Phase 2: Plan Review & Permitting (4-5 Months)
•
•
•
•
Submit completed drawings and plans to the city for official review.
Work with local authorities to obtain necessary permits and approvals.
Address any city-mandated modifications to site plans or construction documents.
Finalize contractor agreements, securing the necessary builders and subcontractors.
Phase 3: Construction & Development (6-10 Months)
•
•
•
•
Month 6: Begin site preparation, grading, and foundation work.
Month 7-8: Vertical construction, including structural build-out and utility installations.
Month 9-10: Interior build-out, smart security installation, and unit customization.
Marketing efforts intensify to attract pre-leasing commitments.