Page 9 - Facilities Highlights 2020
P. 9

 Planned Projects for 2021
  JANSSEN BIO
Project Hot phase 2
Heat pump installation new admin building
VISIONCARE
WP upgrade
ACMS wireless temperate sensor upgrade
HVAC upgrades
Additional utilities metering
Water recycling
Line retrofits for 48, 16, 45,
PV project
WWTP pond liner replacement
PG recycling
Warehouse upgrade - office and loading docs
BMS Upgrade
Scope 3 emissions deep dive
HP Compressed Air B2
Chilled Water Remote monitoring
DSU scheme
Emergency lighting upgrades
Automation room
Line 58, and 70 installation
Fire Alarm Upgrade
Carbon footprint reduction project
B2 Warehouse upgrades
Canteen change room and Nurture room B2
Bulk diesel storage tank
Manufacturing lighting upgrades
Steam upgrades phase 1
Oxygen monitoring phase 2
Bio-Diversity Hub
Site space utilisation project
Poly waste compactor installation
Waste water treatment project/connection to main network
                                     JANSSEN PHARMA
Yellowline Implementation
6S Office programme implementation
DEPUY
Heat recovery from Oberlins
B1 Dust Extraction optimisation
         Carpark Upgrade
Workplace Experience
CIM Enviro B2
AHU-911 optimisation project
                               