QUALIFICATIONS  |  Project Management Services  23





















               •  Reviewing  all  requests  for  clarification  of   •  Implement  corrective  measures  to  address
                  the  Plans  and  Specifications  to  the  Project   and  resolve  all  punchlist  items  or  defect  or
                  Architect which requests shall be directed to   warranty  claims  and  enforcing  all  warranties
                  the  Project  Architect  with  a  copy  to  Project   and guaranties and document the same.
                  Manager.  Project Manager shall follow through
                  by  making  sure  that  proper  clarifications  are   •  In  connection  with  the  completion  of  the
                  issued  by  the  Project  Architect.    All  material   Project or an applicable portion of the Project,
                  clarifications shall be noted in the Plans and   Project  Manager  shall  cause  to  be  delivered
                  Specifications and shall be dated and initialed   to Owner the items constituting evidence of
                  by the party issuing the same.              Completion of the Project or portion thereof.

               •  Hold  weekly  Project  meetings  with  the   •  Provide such other services which are
                  appropriate Project Architect, Consultants and   necessary to the completion of the above listed
                  Contractors, and prepare reasonably detailed   Services as may be reasonably requested by
                  and  accurate  minutes  for  all  such  meetings   Owner from time to time in connection with
                  and issue the same to Owner and to any other   the Project.
                  parties reasonably determined by Owner.
                                                          PROJECT BUDGET, CHANGES AND PAYMENT
               •  Use commercially reasonable efforts to guard   Budget
                  Owner against deficiencies in the construction   •  Project  Manager  shall  supervise  construction
                  of the Project, and report any such deficiencies   of the Project to insure that all costs incurred in
                  of which Project Manager may become aware   connection  therewith  are  equal  to  or  less  than
                  to Owner and the Project Architect, and use   the amounts set forth in the Preliminary Project
                  commercially reasonable efforts to implement   Budget,  and  the  Final  Project  Budget  when
                  procedures required to cure such deficiencies.    developed  (the  Preliminary  Project  Budget  and
                  If  Project  Manager  or  Owner  become  aware   the  Final  Project  Budget  are  sometimes  herein
                  of  any  material  fault  or  defect  in  the  Project   collectively  called  the  “Budget”).    The  Budget
                  or non-conformance with the Final Plans and   shall  constitute  a  major  control  under  which
                  Specifications,  (i)  Project  Manager  or  Owner,   Project  Manager  shall  manage  the  Project.    No
                  as applicable, shall give prompt written notice   expense may be incurred or commitments made
                  thereof to the other and the appropriate   by  Project  Manager  which  exceed  the  amount
                  Contractor(s)  and  (ii)  after  consultation   allocated  to  such  item  in  the  Budget,  nor  may
                  with  each  other,  Project  Manager  shall  take   the  entire  Budget  be  exceeded  without  the
                  whatever corrective action that Owner may   Approval of Owner.  If substantial discrepancies
                  deem necessary to remedy such fault, defect   in the Budget occur or are anticipated by Project
                  or non-conformance.                       Manager,  Project  Manager  shall  notify  Owner
                                                            immediately of the expected change and prepare
               •  Participate  in  scheduled  inspections,  as   and  submit  to  Owner  a  detailed  analysis  of  the
                  appropriate,  made  by  representatives  of   cause and anticipated impact of the change.
                  the  Project  Architect,  Owner,  lenders  or
                  governmental agencies.