Page 121 - 2016 Budget, Bond and Innovation Recommendations
P. 121
West Middle School
5151 South Holly Street
Greenwood Village, Colorado 80111
Year Opened 1966
Current Square Footage 158,500
Site Acreage 18.03
west.cherrycreekschools.org
Proposed Investment 2016 Proposed Improvements
$ 750,000 Innovation
Asphalt and concrete work; fire protection system upgrades; roof
$1,130,120
replacement; track resurfacing
Bond Year Facility Improvement History
Classroom, gym, and cafeteria additions; technology lab and
1990
administrative area renovations
2003 Windows, HVAC system, and roof replacements
Classroom, science area, technology infrastructure, flooring/carpet,
door/hardware, lighting, electrical system, and plumbing upgrades;
2008
ceiling and sanitary sewer replacements; HVAC system renovations; fire
suppression system installation
Security camera and DVR to digital IP system upgrades; mechanical
2012
system replacements; tennis court resurfacing
119