Design Schedule
TASK NAME DAYS START FINISH
15 Months
2017 2018 2018
Pre Design Development Activities
Field survey of entire project Master plan refinement
Phase I & II Design Stage
Preliminary plan development (30%) Design development (90%)
Bid documents
Kickoff meetings with City staff
Public involvement
Inventory and analysis
85
40
80
265
45
11/6/2017
11/6/2017
11/13/2017
11/13/2017
1/8/2018
1/8/2018
3/5/2018
3/2/2018
5
11/10/2017
1/5/2018
3/2/2018
3/2/2018
1/11/2019
2/9/2018
5/4/2018
11/10
1/5
Utilities mapping SUE
80
11/13/2017
3/2/2018
3/2
3/2
80
11/13/2017
3/2
25
2/9
5/4
Conceptual plan development (60%)
45
55
5/7/2018
7/9/2018
7/6/2018
9/21/2018
7/6
9/21
Final design development of plan and specifications (100%)
65
20
9/24/2018
9/24/2018
12/21/2018
10/19/2018
10/19
12/21
Permit Acquisition
80
9/24/2018
1/11/2019
1/11