On completion of stabilization with RoadCem and final compaction the surface of the road is primed with aquous cold bitumen spray (Figure 5.49).
Figure 5.49 Cold Aquaous Bitumen Priming.
Figure 5.50 Applying chiped stone.
Immidiately a layer of Chip Stone of appropriate size (5 to 13 mm depending on the desired rougness) is placed on top of the primed layer (Figure 5.50)
The surface is than compacted statically. If more than one layer is to be applied the procedure is repeated for each layer.
The finished road surface is shown in Figure 5.51.