Page 9 - The Hollows RFP
P. 9
MARCH
Week of 19th
CRITICAL PATH
• 23rd March Finalized Builder Request For Proposal (send out NLT Monday 26th)
Week of 26th
• Sales Leadership Completes Builder Interest conversations and seeks conditional statement of interest (CSOI) • Ownership Selects Three Builders for 85/100’ segment
• Initial review of amenity improvements (Community Club ‘Trailhead’, campground, trails, kayak club)
APRIL
Week of 2nd
• Developer integration with The Hollows Property Owners’ Association
Week of 23rd
• Flags install, arrival sequence and signage improvements begin
MAY
Week of 14th
• Realtor Dusty Boot Tour Event
• May 17th Builder Reveal Event and press release announcing Builder Partners and Legacy Communities.
Anticipated location: The Domain
Week of 21st
• Initiate Discovery Center Construction
• May 26th VIP The Hollows Homeowner Referral Night and Memorial Day Event at Beach Club (464 current
owners and 220 slip lessees invited)
JULY
Week of 2nd
• Discovery ‘sales’ Center Opens
• 85’s/100’s segment builders begin presale operations\
SEPTEMBER/OCTOBER
• The Hollows Community Grand Opening
• Initial Amenity Improvements Complete (exception of Community Club ‘Trailhead’)
SPRING 2019
• Groundbreaking of New Community Club ‘Trailhead’ • Introduce new neighborhood(s)
DEVELOPMENT & MARKETING SCHEDULE
4