Page 533 - Appeal bundle 31 files
P. 533
Appeal Bundle
and in accordance with the approved programme. If no unexpected
contamination is encountered during development works, on completion of
works and prior to occupation a letter confirming this should be submitted
to the LPA. If unexpected contamination is encountered during
development works, on completion of works and prior to occupation, the
agreed information, results of investigation and details of any remediation
undertaken will be produced to the satisfaction of and approved in writing
by the LPA.
Environmental Health Officer
Due to the proximity of adjacent residential premises, should the application be approved,
the following conditions aimed at minimising disturbance to residential amenity during
demolition and construction are recommended. In addition, the proximity of this site to a
busy A road suggests that existing background noise levels are likely to be fairly high due to
traffic. A condition is therefore recommended to protect the amenity of future residents:
Construction hours: Works of demolition or construction, including the use of plant and
machinery, necessary for implementation of this consent shall be limited to the following
times:
Monday to Friday 08:00 - 18:00 Hours
Saturday 09:00 - 13:00 Hours
Sundays and Bank/Public Holidays no work permitted.
Reason: to protect the amenity of local residents.
Deliveries: Deliveries or collection of plant, equipment or materials for use during the
demolition/construction phase shall be limited to the following times:
Monday to Friday: 08:00 - 18:00 hrs;
Saturday: 09:00 - 13:00 hrs
Sunday & Public/Bank holidays: None permitted
Reason: to protect the amenity of local residents.
Control of Demolition/Construction noise: Demolition/Construction work shall not
commence until a scheme for the protection of neighbouring properties from noise generated
during demolition/construction work has first been submitted to, and approved in writing by,
the Local Planning Authority. The scheme shall be in accordance with BS5228-1:2009
'Noise and Vibration control on construction and open sites'. The scheme as approved shall
be operated at all times during the demolition/construction phases of the development.
Reason: To protect neighbouring residents and residences from noise and vibration.
Minimise dust emissions: Demolition/Construction work shall not commence until a
scheme for the protection of the existing neighbouring properties from dust has been
submitted to, and approved in writing by, the local planning authority. The scheme as
approved shall be operated at all times during the demolition/construction phases of the
development.
Reason: to protect the amenity of local residents from dust emissions.
BATES N0 000530