2/27/24, 10:28 AM                               Work on restoration of 2.1-km Deira pier under way
        Work on restoration of 2.1-

        km Deira pier under way

        DUBAI, 22 hours, 10 minutes ago
        Dubai  Municipality  has  begun
        implementing a key project for the
        reconstruction  and  rehabilitation
        of  the  supporting  walls  along  the
        Deira side of Dubai Creek.

        It  is  aimed  at  enhancing  the
        effectiveness    of    the   creek’s
        retaining  walls  by  upgrading  the
        dock, reconstructing sections that
        have     been      damaged       and
        dilapidated  over  the  past  50
        years,  and  preventing  potential
        flooding  during  harsh  weather
        conditions.

        The AED112 million ($30.4 million) project is being implemented in two phases, with the first one
        involving the restoration of a 2.1 km stretch along the Deira side of Dubai Creek.

        Dubai  Municipality  said  the  site  will  be  divided  into  multiple  sections,  and  each  segment  will  be
        sequentially patterned to ensure uninterrupted docking traffic. The second phase will cover a 2.3 km
        length on the Bur Dubai side.

        The  project's  14-month  timeline  includes  the  restoration  of  the  2.1  km  Deira  pier,  which  involves
        replacement and the rehabilitation of damaged sections of the concrete wall, reaching a depth of 8
        meters and increasing its height to 3 meters. These improvements aim to ensure the safe docking of
        ships in the area.

        By initiating this project, the Municipality aims to enhance services and facilities for safe docking and
        navigation, which will be ensured through the provision of 200 anchors across the dock. The entire
        work will be completed within a 14-month period.

        "The  project  highlights  Dubai  Municipality’s  commitment  to  transforming  the  emirate  into  a  more
        attractive  and  innovative  city  by  enhancing  various  elements  and  services  it  offers  through  the
        strategic  and  sustainable  development  of  all  coastal  facilities  and  infrastructure,"  remarked  its
        Director-General Dawoud Al Hajri.

        "The  project  is  set  to  improve  security  and  safety  measures  for  maritime  traffic  and  commercial
        operations within Dubai Creek, he noted.

        As a significant symbol of the city’s growth, Dubai Creek serves as a vibrant artery at the heart of
        Dubai.  Facilitating  the  passage  of  over  13,000  ships  annually,  it  plays  a  key  role  in  fostering  the
        economic and social prosperity of the emirate.

        "We have implemented several measures to mitigate the risks posed by climate change and rising
        sea levels, closely monitoring changes on both sides of the creek. Furthermore, we have conducted
        technical studies to devise construction designs that can enhance the efficiency of the marine docks
        on both banks, said Al Hajri.
      https://tradearabia.com/news/CONS_419339.html                                                                 1/2