Page 31 - ENGLISH PR REPORT FEBRUARY 2024_Neat
P. 31

fostering the economic and social prosperity of the emirate. Additionally, the creek


               further supports commercial dealings with neighboring markets in the region.”


               “We have implemented several measures to mitigate the risks posed by climate

               change and rising sea levels, closely monitoring changes on both sides of the creek.

               Furthermore, we have conducted technical studies to devise construction designs


               that can enhance the efficiency of the marine docks on both banks. These designs

               adhere to the highest global standards, ensuring the preservation of the supporting

               walls’ stability and safeguarding against increased flooding during seasonal weather

               conditions.” Al Hajri added.






               Comprehensive work


               The project's 14-month timeline includes the restoration of the 2.1 km Deira pier,

               which involves replacement and the rehabilitation of damaged sections of the

               concrete wall, reaching a depth of 8 meters and increasing its height to 3 meters.

               These improvements aim to ensure the safe docking of ships in the area.



               By initiating this project, the Municipality aims to enhance services and facilities for

               safe docking and navigation, which will be ensured through the provision of 200

               anchors across the dock.
   26   27   28   29   30   31   32   33   34   35   36