Page 15 - BENTLEY SYSTEMS PR REPORT - APRIL 2024
P. 15

4/3/24, 2:55 PM                                    Ensuring smooth site logistics at Diriyah
        The KEO team was tasked with managing construction for all these assets on the vast project site that could
        expand to 14 sq km in the future.

















































                                                     Marion Bouillin


        For this project, KEO was responsible for providing safe, uninterrupted site access, as well as traffic and

        construction planning. It faced coordination and technical challenges to deliver over 66 assets in a short
        timeframe, all while managing public transport during construction.


        Clash detection was a priority because it would ensure that the design did not have overlapping components,

        saving time and avoiding errors during construction. However, when searching for the right software, it quickly
        encountered a problem.



        “Most of the available software options did not account for the timing aspect of clashes, rendering them
        unsuitable for our needs,” says Juan Tena Florez, Digital Services Director at KEO.


        KEO needed software to not only handle clash detection, but also provide 4D construction simulations to ensure

        safe and timely project delivery.




      https://www.gulfconstructiononline.com/Article/1628164/Ensuring_smooth_site_logistics_at_Diriyah              2/4
   10   11   12   13   14   15   16   17   18   19   20