Page 3 - CT
P. 3
Chittapur Category- NSG 5
A Works completed in the last three years (Rs. In '000s)
Sl.No Name of work PH 2018-19 2019-20 2020-21
1 SC Division- Provision of Divyang facilities at D,E, F category PA 500
stations
2 Provision of Energy efficient lighting in waiting hall PA 750
concourse and platform area including glow signages,
water coolers
3 Chittapur - Provision of CIBs at CT Station. PA 4000
PA Total 5250
B Works in Progress (Rs. In '000s)
Year of Cost TDC
sanc Name of work PH Remarks
2019-20 Chittapur~~Extension of existing FOB at Chittapur station. PA 19000 Oct'21 FOB footings concrete
work completed.
Stanchion erected. Girders
under fabrication.
2019-20 Provision of Chlorinators at CT station. PA 834 Dec'21 Work is in progress.
PA Total 19834
2019-20 Chittapur~~Augmentation/improvement of Running room OSW 19998 Dec'21 Work is in progress.
capacity at CT
OSW Total 19998
Summary(Fig in Rs.000's)
PH Completed In progress Total
PA 5250 19834 25084
OSW 0 19998 19998
Total 5250 39832 45082