Page 3 - Engineering
P. 3
TSR(S) :
Progress of 4.434 TKM has been
achieved against proportionate
target of 1.91 TKM (upto Oct‟21) and
annual target of 3.27 TKM. The
percentage of performance is
232.147%.
TFR :
Progress of 173.024 TKM has been
achieved against proportionate
target of 141.44 TKM (upto Oct‟21)
and annual target of 242.46 TKM. The
percentage of performance is 122.33
%.
DEEP SCREENING OF PLAIN TRACK BY
BCM:
Progress of 120.19 TKM has been
achieved against proportionate
target of 87.7 TKM (upto Oct‟21) and
annual target of 150 TKM. The
percentage of performance is
137.047%.
DEEP SCREENING OF T/O BY BCM,T-28
& ROAD CRANES:
Progress of 36 Nos has been achieved
against proportionate target of 44 Nos
(upto Oct‟21) and annual target of
75 Nos. The percentage of
performance is 81.81%.