Page 6 - ENGINEERING
P. 6
3.2.2 TRACK STRUCTURE:
52 Kg 72 UTS 52 Kg 90 UTS 60Kg
SECTION Total
PSC6 PSC5 PSC6 PSC5 PSC-6
WADI-SNF ( DN ) - 0.80 7.27 9.74 153.84 171.65
SNF-WADI (UP ) 0.12 0.12 13.90 6.12 151.39 171.65
TOTAL 0.12 0.92 21.17 15.86 305.23 343.30
Formation: Mostly silty and black cotton soil.
3.2.3 LEVEL CROSSINGS ON SC-WD SECTION
Non-
Class Manned Interlocked
interlocked
Traffic 5 5 -
Spl. Class
Engg. 1 1 -
Traffic 1 1 -
A Class
Engg. 2 1 1
Traffic - - -
B1 Class
Engg. - - -
Traffic - - -
B2 Class
Engg. 1 - 1
Traffic 1 1 -
C Class
Engg. 2 - 2
TOTAL 13 9 4
3.2.4 BRIEF DETAILS OF BRIDGES ON VKB-KOHR SECTION
Type of Bridge No of Bridges
Important 0
Major 67
Minor 393
3.2.5 MAJOR SIDINGS:
CHITTAPUR : Orient Cement Siding
MAILKHAID ROAD : Ultra tech Cement siding I & II
SERAM : Vasavadatta Cement Siding,
Tandur : Cement Corporation of India, India Cements Ltd.,
Penna Cements Ltd., Kalburgi Cement Siding, & CCL.
SHANKARPALLI : Ultratech Cements Ltd. S.V. Multi Logitech (P) Ltd.,
NAGALAPALLI : SAIL, CONCOR, RINL
3.2.6 PERMANENT SPEED RESTRICTIONS:
17Nos on DN line – KM: 177/0-KM: 3/0 between HSJ-WD stations
17Nos on UP line – KM: 3/0-KM: 177/0 between WD –HSJ stations