3.1.2 TRACK STRUCTURE:
52 Kg 72 UTS 52 Kg 90 UTS 60Kg
SECTION Total
PSC6 PSC5 PSC6 PSC5 PSC-6
SNF-SC ( DN ) 0.33 5.70 8.48 14.51
SNF-SC (UP ) 1.52 1.43 11.56 14.51
TOTAL 1.85 7.13 20.04 29.02
Formation: Mostly silty and black cotton soil.
3.1.3 LEVEL CROSSINGS ON SNF-SC SECTION
Class Manned Interlocked Non-interlocked
Traffic
Spl. Class
Engg. 2 2
Traffic
A Class
Engg.
Traffic
B1 Class
Engg.
Traffic
B2 Class
Engg.
Traffic
C Class
Engg.
TOTAL
3.1.4 BRIEF DETAILS OF BRIDGES ON SN-SC SECTION
No of Bridges
Type of Bridge
HYB-HSJ SNF-SC
Important 0 0
Major UP-2,DN-2 UP-6,DN-6
Minor UP-8, DN-8 UP-19,DN-19
3.1.5 MAJOR SIDINGS:
SANATHNAGAR : FCI Siding, Goods complex, IOH siding.
3.1.6 PERMANENT SPEED RESTRICTIONS:
7Nos on DN line – KM: 1764/4-KM: 194A/24 between SNF-SC stations
8Nos on UP line – KM: 176/2 -KM: 194A/23 between WD –HSJ stations
2Nos on DN line – KM: 189/18A-KM: 184/16 between HSJ-HYB stations