Page 2 - MECH(C&W)
P. 2

being done at SNF depot. Material is supplied by M/s CONCOR
                     for 315 wagons and up gradation is done departmentally at SNF

                     during ROH attention on 300 BLC wagons till now.

               v.    Tyre turning of wheel sets for BLC/BOXN wagons at Pit Wheel lathe of
                     SC  depot:  Tyre  turning  of  829  defective  wheel  sets  of  BLC/BOXN
                     wagons was carried out at Pit wheel lathe of SC coaching depot
                     during  the  year  2021-22(Apr  Oct).  Earlier  defective  wheels  were

                     being  sent  from  SNF  to  RDM  for  tyre  turning.  This  system
                     improvement  has  avoided  the  movement  of  lorry  from  SNF  to
                     RDM  and  back  for  tyre  turning  of  wheel  sets  thereby  saving  lot  of
                     time and money.


               vi.                                                 : 840 wagons were attended by
                     giving  intense  repairs  at  RDM  &  BPA  freight  depots  during  the
                     current year 2021-22(Apr Oct).

               vii.  Quick  Watering  System  at  SC  station:  Quick  coach  watering
                     system  has  been  fully  automated  at  Secunderabad  Station  to

                     reduce  the  time  taken  for  filling  the  water  in  the  coaches.  To
                     achieve this existing pumping system has  been replaced with a
                     New  Automatic  Coach  watering  system  having  6  nos.  of  20  HP
                     pumps.

               viii.  Installation  of  surveillance  system  of  CC  cameras:  At  locations  of

                     Railway  Owned  EIMWBs  installed  at  SUH,  SKP,  CHZ,  KZJ,  HSP,  STBD,
                     MAGH and TNGM stations, the surveillance system of CC cameras
                     is commissioned and can be monitored online. Provision of cameras
                     in remaining two Weigh bridges(SC & HYB), where VPH is weighed,
                     under process.




























               ix.  Installation and Commissioning of Online Monitoring of Rolling Stock
                     (OMRS): New Online Monitoring of Rolling Stock (OMRS) on Dn Main
                     line near SKZR station in BPQ-WL section has been commissioned
                     on  29.01.2021.  This  is  used  to  identify  following

                                                                                                        2
   1   2   3   4   5   6   7