1. GENERAL PERFORMANCE STATISTICS
1.1. TRACK
1.1.1. PERFORMANCE OF TRACK WORKS
CTR UNITS :
Progress of 51.529 TKM has been
achieved against proportionate
target of 49.66 TKM (upto Oct‟21)
and annual target of 85.14 TKM. The
percentage of performance is
103.764%.
TRR(P) :
Progress of 64.75 TKM has been
achieved against proportionate
target of 72.92 TKM (upto Oct‟21)
and annual target of 125 TKM. The
percentage of performance is
92.91%. Less progress is due to
less supply of rails.
TSR(P):
Progress of 17.112 TKM has been
achieved against proportionate
target of 12.25 TKM (upto Oct‟21)
and annual target of 21 TKM. The
percentage of performance is
139.69%. Annual target has been
achieved.
TRR(S) :
Progress of 16.761 TKM has been
achieved against proportionate
target of 12.25 TKM (upto Oct‟21)
and annual target of 21 TKM. The
percentage of performance is
136.824%.