BEGUMPET                                                                 Category-NSG 4


             A     Works completed in the last three years                                                    (Rs. In '000s)

           Sl.No                           Name of work                                PH        2018-19       2019-20              2020-21
             1     Provision of cover over platform on PF No. side on SC end at        PA                                             5600
                   BMT station for a length 65 mts.

             2     SC Division- Provision of Divyang facilities at D,E, F category     PA                                             500
                   stations
             3     BMT Provision of Cover over Platform on PF no.1 side on             PA                                             5592
                   Secunderabad End at BMT station for a length of 65 mts.
                                                                         PA Total                    0            0                  11692

             B     Works in Progress                                                                          (Rs. In '000s)

           Year of
            sanc                           Name of work                                PH          Cost          TDC                Remarks
           18-19   Begumpet :- Improvements to RPF outpost at BMT station             SW           2480        Dec'21    Brick work is in progress.
                   under SSE/W/HYB.
                                                                         SW Total                  2480
           19-20   Extension of platforms at BMT station.                              PA          3597        Mar' 22   Estimate sanctioned. Tender
                                                                                                                         to be called.
                                                                         PA Total                  3597

                                                                                                          Summary(Fig in 000's)
                                                                                       PH      Completed     In progress              Total


                                                                                       PA         11692         3597                 15289

                                                                                      SW             0          2480                  2480
                                                                                      Total       11692         6077                 17769