             A    Works completed in the last three years                                                       (Rs. In '000s)

           Sl.No                             Name of work                                 PH       2018-19      2019-20             2020-21

             1    SC Division- Provision of Divyang facilities at D,E, F category         PA                                          500
                  stations

                                                                             PA Total                                                 500


             B    Works in Progress                                                                             (Rs. In '000s)


           Year of                           Name of work                                 PH         Cost         TDC               Remarks
            sanc

           18-19 Raising of platforms from Low/Medium Level to High Level over            PA         3561       Dec'21     UP platform completed
                  various stations in West section.                                                                        except Miscellaneous works in
                                                                                                                           progress .
                                                                                                                           DN platform raising of PF
                                                                                                                           completed, earth work filling
                                                                                                                           completed 90%. VDC and
                                                                                                                           platform
                                                                                                                            wall and other MISC works to
                                                                                                                           be done.
                                                                              PA total               3561

                                                                                                          Summary(Fig in Rs.000's)
                                                                                          PH      Completed In progress               Total


                                                                                          PA          500         3561                4061
                                                                                         Total        500         3561                4061