KDC CORPORATE OFFICE DEVELOPMENT DURING THE PAST FIVE YEARS




                  CORPORATE TENANT                           LEED              SIZE             SCHEDULE                                STATUS                               TRANSACTION TYPE

           State Farm Regional HQ at CityLine                             2,100,000 SF           42 Months                    Complete: 9,000 Employees                     NNN Lease / Open Book


                   Raytheon at CityLine                                    489,000 SF            15 Months                    Complete: 1,500 Employees                     NNN Lease / Open Book

     Toyota Motor North America HQ at Legacy West                         2,100,000 SF           30 Months                    Complete: 7,000 Employees                         At Risk Dev Fee


         Liberty Mutual Insurance at Legacy West                          1,100,000 SF           26 Months                    Complete: 5,500 Employees                     NNN Lease / Open Book

      JPMorgan Chase Regional HQ at Legacy West                           1,500,000 SF           21 Months                    Complete: 6,000 Employees                  At Risk Dev Fee / Land Owner


             FedEx Office HQ at Legacy West                                265,000 SF            12 Months                    Complete: 1,100 Employees                     NNN Lease / Open Book

               State Farm Data Centers (2)                 Pending         300,000 SF            16 Months                     Complete: 100 Employees                            NNN Lease

                      Frost Bank HQ                                        500,000 SF            24 Months                    Complete: 1,700 Employees                     NNN Lease / Open Book


                  Independent Financial                                    159,000 SF            12 Months                     Complete: 400 Employees                          At Risk Dev Fee

              Pioneer Natural Resources HQ                                1,125,000 SF           25 Months                    Complete: 2,500 Employees                     NNN Lease / Open Book


                       Epic Phase I                                        250,000 SF            24 Months                    Complete: 2,200 Employees                         At Risk Dev Fee

                    Uber, Epic Phase II                                    500,000 SF            30 Months          Underway (2022 Completion): 3,000 Employees                 At Risk Dev Fee


                       Credit Suisse                                       400,000 SF            15 Months          Underway (2020 Completion): 3,900 Employees                 At Risk Dev Fee

          State Farm at Park Center Regional HQ                           1,750,000 SF           39 Months          Underway (2020 Completion): 9,000 Employees              Fee Dev / Open Book

                  Baylor Scott and White                   Pending         300,000 SF            23 Months                    Complete: 1,500 Employees                         At Risk Dev Fee


                     SRS Distribution                      Pending         100,000 SF            14 Months                     Complete: 500 Employees                            NNN Lease

                Sammons Financial Group                    Pending          217,000 SF           16 Months           Underway (2021 Completion): 700 Employees                  At Risk Dev Fee


                   Raytheon McKinney                       Pending         200,000 SF            14 Months           Underway (2021 Completion): 500 Employees                  At Risk Dev Fee

                  TOTAL LAST 5 YEARS                                      13,355,000 SF      22 MONTHS AVG                       56,100 EMPLOYEES