Page 34 - KDC Park Heritage_Amazon_1.11.21_presentation
P. 34

CORPORATE TENANT                                SIZE              SCHEDULE                                  STATUS                                  TRANSACTION TYPE


              State Farm Regional HQ at CityLine                 2,100,000 SF          42 Months                      Complete: 9,000 Employees                         NNN Lease / Open Book

                      Raytheon at CityLine                        489,000 SF            15 Months                     Complete: 1,500 Employees                         NNN Lease / Open Book


       Toyota Motor North America HQ at Legacy West              2,100,000 SF          30 Months                       Complete: 7,000 Employees                            At Risk Dev Fee


           Liberty Mutual Insurance at Legacy West               1,100,000 SF          26 Months                      Complete: 5,500 Employees                         NNN Lease / Open Book


        JPMorgan Chase Regional HQ at Legacy West                1,500,000 SF          21 Months                      Complete: 6,000 Employees                      At Risk Dev Fee / Land Owner


                FedEx Office HQ at Legacy West                    265,000 SF            12 Months                     Complete: 1,100 Employees                         NNN Lease / Open Book


                  State Farm Data Centers (2)                     300,000 SF            16 Months                      Complete: 100 Employees                                 NNN Lease

                         Frost Bank HQ                            500,000 SF           24 Months                      Complete: 1,700 Employees                         NNN Lease / Open Book


                     Independent Financial                        159,000 SF            12 Months                      Complete: 400 Employees                              At Risk Dev Fee


                 Pioneer Natural Resources HQ                    1,125,000 SF          25 Months                      Complete: 2,500 Employees                         NNN Lease / Open Book


                           Epic Phase I                           250,000 SF           24 Months                      Complete: 2,200 Employees                             At Risk Dev Fee

                       Uber, Epic Phase II                        500,000 SF           30 Months            Underway (2022 Completion): 3,000 Employees                     At Risk Dev Fee


                          Credit Suisse                           400,000 SF            15 Months           Underway (2020 Completion): 3,900 Employees                     At Risk Dev Fee


            State Farm at Park Center Regional HQ                1,750,000 SF          39 Months            Underway (2020 Completion): 9,000 Employees                   Fee Dev / Open Book


                     Baylor Scott and White                       300,000 SF           23 Months            Underway (2020 Completion): 1,500 Employees                     At Risk Dev Fee


                        SRS Distribution                          100,000 SF            14 Months            Underway (2020 Completion): 500 Employees                         NNN Lease


                   Sammons Financial Group                        217,000 SF            16 Months            Underway (2021 Completion): 700 Employees                      At Risk Dev Fee

                     TOTAL LAST 5 YEARS                         13,155,000 SF      22 MONTHS AVG                          55,600 EMPLOYEES