Page 56 - HSE -Zero is Possible_v1.0
P. 56

Chekka Cement Plant
           LEBANON  Cement  Ready to fight the fire
                           Liquid Fuel Fire





                           Description
                                                   Results/Impacts
                           Fully automatic
                           fire fighting system
                                                    preparedness
                           implemented in the liquid   •  Improved emergency
                                                   •   Increased competency
                           fuel areas with the support   and discipline of the
                           of third party expert.   operations team
                           Routine maintenance,
                           training and periodic   This project is considered
                           drills were put in place to   as the reference in
                           ensure effective operation   fire protection on fuel
                           over time.              installations in Lebanon
                                                   amongst all other
      Jamil Bouharoun      Key success factors     industries according to
          CEO              •  External expertise to   the supplier.
                            initiate the project
                           •  Active participation
                            in drills, training, and     Leak Free System
                            comprehensive testing      Alarms, Interlocks &
                           •  Excellent housekeeping   Trips
                            in the area                Early detection of
                           •  Approx 1.2M CHF CapEx  creeping failure
                                                       Explosion mitigation
       Grace Elazar                                  & firefighting
       Head of HSE






         Liquid Fuel Fire
    44