Page 38 - Zero is Possible - Volume 3
P. 38

Orizaba
                         Water
           MEXICO  Cement  Turning wastewater


                         to clean water


                         Opportunity
                                                 •  Achieved a 51%
                         Implementation of
                         technologies to improve   Results
                                                  reduction in specific
                         water efficiency and     freshwater withdrawal in
                         reduce the plant's water   2024 vs. 2023
                         footprint.              •  Contributed to a 23%
                                                  overall reduction in
                         Solution                 Holcim Mexico’s total
                         •  Drone inspection of   water footprint
                           pipelines from wells to   •  Marked significant
      Christian Dedeu      processing area        progress toward
          CEO            •  Updated hydraulic and   Holcim’s global water
                           water line network     efficiency targets
                         •  Redesigned return system
                          with high-pressure pump
                          and backup
                         •  Recovered pump parts
                           via 3D metal printing
                         •  Installed flowmeter to
                           track water return to
     Óscar Araya Sanchez   clarifier
       Head of HSE
                         Cost: 9.3 kCHF
                         Timeline: 1 year