PHILIPPINES Cement All sites
Mobile Equipment
Incident
Shielding workers against
moving forklifts!
Opportunity Cost: 4 kCHF per site
Shared spaces between (segregation);
pedestrians and forklifts 0 CHF for projection lights
in cement warehouses (included in contract)
posed a constant collision Timeline: 6 months
risk. A clear system was
needed to separate and Results
protect people from moving • Zero incidents: No
Nicolas George equipment. pedestrian-forklift
CEO
collisions since 2023
Solution • Full coverage: 34 forklifts
Warehouses were equipped with Forklift
redesigned to enforce strict Safety Zone Projection
segregation using marked Lights across all sites
walkways, physical barriers, • Safer flow: Clear, risk-
and forklift-only zones. free movement paths for
All forklifts were also fitted people and vehicles
with the Forklift Safety Zone • Workforce awareness:
Catherine Joy Guinto Projection Light system to Improved discipline and
Head of HSE
further prevent close contact. respect for designated
zones