Civils/Urban Regeneration Letterkenny Flood Risk Mitigation Works
Project Location
Value Description
Client Design Team
Letterkenny General Hospital, Letterkenny, Co.Donegal
€ 0.8m
Construction of a 500m, 1300mm diameter concrete pipeline, to depths
of 7m in rock, to alleviate flood water from Sprackburn Tributary.
Including 10nr precast manholes,
34m of interceptor channel, trashscreens, headwalls and monitoring station.
HSE Estates
Tobin Consulting Engineers
Key Packages
•Groundworks and trench excavation. •Precast structures- manholes,
headwalls and trashscreens. •M&E for flood monitoring. •Extensive rock breaking.
Key Deliverables
•Work carried out within the confines of the existing acute hospital campus.
•Environmental controls, dust control to reduce risk of Aspergillus infection.
•Noise and security monitoring due to adjacency to mental health facility.