Page 117 - Untitled-1
P. 117
96 ESTIMATING TASK DURATIONS
Skill Levels, Learning Curves, and Priorities How do we handle potential perfor-
mance modifiers? Do we add time to the duration estimate because we expect that
there will be additional time and effort needed to do the task the first time (learn-
ing curve)? Should the duration be adjusted based on the skill level of the re-
sources expected to be assigned? Do we actually have an index of skill level? And
what if the resources change? Does a higher priority task or project get done faster
because of the pressure and attention? These are all things that can impact upon
the task duration. But there rarely is a set of guidelines in place to help us with the
estimating and to aid in achieving consistency across the project and the team.
PERT Method This technique provides for a quantitative method of considering
uncertainty or risk. It calls for the use of three time estimates for each task. These
are called optimistic, most likely, and pessimistic. The most likely is the duration
that can be expected 50 percent of the time. The optimistic is the shortest reason-
able duration, attainable about 10 percent of the time. The pessimistic is the
longest reasonable duration, also with about a 10 percent probability. In the
PERT method, a PERT duration is calculated, usually based on the formula: (a +
4b + c)/6, where b is the most likely. Using special software, it is then possible to
perform a statistical analysis, providing a calculated probability of meeting any
project end date. Although it may appear that the PERT method takes a great
deal of additional effort, the reverse is really true. In reality, we tend to go
through the process of thinking of the possible range of estimates, based on per-
ceived risk and uncertainty. But then, after mentally deriving a single duration,
we fail to capture the information that went into the estimate.
Tool Tip Special software is available to support the PERT
method of schedule computation. Among the most popular
are two products that work with Microsoft Project. These are:
Risk + for Project (CS Solutions) and @ Risk for Project (Palisade
Corporation).
Welcom Software Technology and Primavera Systems also
have offered tools to support the PERT method. These, Opera
and Monte Carlo, work with the CPM products sold by these
vendors: Open Plan and Primavera Project Planner.
Both Microsoft and Scitor have provisions for using three
time estimates, but do not provide full statistical calculation of
schedule probabilities. Scitor (PS7 and PS8) allows the user to
vary the weighting of the three estimates.